Bidder Inquiries

Sign In | Create Account

Viewing inquiries for 04-1G8404

Submit new inquiry for this project


Inquiry #1: We are counting different totals for the APS at all three locations (E-2 & E-3, E-5, and E-8 & E-9). Please confirm the APS Quantities on Plan Sheet EQ-1.
Inquiry submitted 10/15/2017

Response #1:Submitted for consideration.
Response posted 10/16/2017


Response #2:The number of APS's shown on the EQ-1 is correct since some will be installed on the signal poles and some on a separate pedestrian pole.
Response posted 10/17/2017




Inquiry #2: How many working days is the Plant Establishment period?
There is a bid item for Plant Establishment but no working days are shown in the Notice to Bidders

Inquiry submitted 10/18/2017

Response #1:Submitted for consideration.
Response posted 10/18/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.


Contracting Information

Statewide Alerts and Other Information