Bidder Inquiries

Sign In | Create Account

Viewing inquiries for 03-2F9804

Submit new inquiry for this project


Inquiry #1: Please confirm there is NOT a prebid for this project.
Inquiry submitted 08/09/2018

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 08/10/2018


Response #2:
There is no pre-bid for this project.
Response posted 08/15/2018




Inquiry #2: A - On Plan Sheet SC-11, bottom of the plan sheet is noted "Stage 4B" while it is also stated to construct this work at "end of Stage 2 before moving southbound lane to Stage 3 configuration". Notation of the "Stage 4B" conflicts with the description written... Should this actually read to construct this work at end of Stage 4 before moving to Stage 5 configuration?

B - On Plan Sheet SC-13, left of plan sheet is noted "Match Stage 4 Traffic Handling Plan". Stage 4 and 5 overlap work areas with differing traffic handling shown in the same work areas. Please clarify what this means...

C - On Plan Sheet SCQ-1, Roadway Items summary the quantities appear to be incorrect after a detailed takeoff was performed indicating the following: 4 EA Alt Temp Crash Cushions in Stage 3, 84 EA Type iii Barricades in Stage 4, 8 EA Type iii Barricades in Stage 5, and 48 EA Type iii Barricades in Stage 6. Please double check to confirm and update bid quantities accordingly.

Inquiry submitted 08/17/2018

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 08/17/2018




Inquiry #3: A - Spec Page 13 says there is a $4700 Water Meter Charge. Is this a refundable deposit or non-refundable?

B - Spec Page 21 states there is to be no stage 3-6 work before April 2020. Is this correct? If correct... Would the stage 1 and stage 2 work occur immediately then crews and equipment demobilize and return in April 2020 or would the stage 1 and stage 2 work start closer to the April 2020 date for a concurrent work schedule?

C - Spec Page 22 for Two Project ID signs... is this payable through Construction Area Signs?

D - Spec Page 24 calls for two arrays of three rumble strips per lane closure. These aren't shown on the traffic control plans. Please confirm they are required.

E - Spec Page 31 states a sound level meter and acoustic calibrator are to be provided to Caltrans by the Contractor? Please confirm and clarify which pay item is to be used for this.

Inquiry submitted 08/20/2018

Response #1:(#3)-Your inquiry has been received and is being reviewed.
Response posted 08/20/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.