Inquiry #1: With the recent determination by DIR that off haul of asphalt and concrete is now covered work, will Caltrans enforce the payment of prevailing wages for off haul trucks on this project?
Inquiry submitted 01/11/2018

Response #1:Your inquiry has been received and is being reviewed.
Response posted 01/11/2018


Response #2:
Yes. Caltrans will enforce the payment prevailing wages for off haul trucks on this project. Please refer to the prevailing wage rate determinations, for the appropriate classification on the Department of Industrial Relations website, located at: https://www.dir.ca.gov/oprl/DPreWageDetermination.htm
Response posted 01/11/2018




Inquiry #2: Reference the "AC Pavement Repair" table on Sheet Q-4. Please confirm the SQYD quantities for the "Cold Plane AC Pavement" column. The math does not work when converting SF to SQYD for the individual Length and Width of Repairs provided. A few are correct, but most do not match the SQYD calculations based on the pavement repair dimensions in the table (ie., some show a 6' width but SQYD calculation is based on a 12' wide repair, etc,...). Please confirm this table and revise plan sheet as necessary.
Inquiry submitted 01/19/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 01/19/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.