Inquiry #1: Could Caltrans please provide PPF files in order to do a proper smoothness analysis prior to bidding?
Inquiry submitted 11/08/2018

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 11/08/2018


Response #2:
Currently, North Region does not provide pre-construction ppf data for mill and fill projects. Please bid per the contract documents.
Response posted 11/08/2018




Inquiry #2: Could Caltrans please provide PPF files in order to do a proper smoothness analysis prior to bidding?
Inquiry submitted 11/08/2018

Response #1:
(#2)-Your inquiry has been received and is being reviewed.
Response posted 11/08/2018


Response #2:
Currently, North Region does not provide pre-construction ppf data for mill and fill projects. Please bid per the contract documents.
Response posted 11/08/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.