Bidder Inquiries

Sign In | Create Account

Viewing inquiries for 02-4G5204

Submit new inquiry for this project


Inquiry #1: How do we arrange for a site visit to include access to the existing catwalk?
Inquiry submitted 03/09/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 03/09/2018


Response #2:
Please bid per the current contract documents.
Response posted 03/15/2018




Inquiry #2: Section 14-6.10C of the SP’s states, “ Install bird exclusion devices such that bird access to the underside of the bridge…is completely blocked.”
Section 14-6.03B of the Sp’s states provides a protective radius of 20 ft for swallows and 50 ft for all other migratory and nongame birds.

Is the intent to completely block access for all birds from the bridge structure or to place exclusion devices to provide a protective radius from the specific work locations?

Inquiry submitted 03/15/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 03/15/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 30, 2018.
Please bid per the current contract documents.
Response posted 03/30/2018




Inquiry #3: Please clarify your response to Inquiry #1. Does this mean the Contractors will have no access to the existing catwalk prior to bid?
Inquiry submitted 03/15/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 03/15/2018


Response #2:
Correct, the Contractors will not have access to the existing catwalk prior to bid. Your attention is directed to the Informational Handout for photographs of the work locations and catwalk. Please bid per the current contract documents.
Response posted 03/26/2018




Inquiry #4: A Stormwater Annual Report is not included in the bid item list. Will there be an Annual Report required for this project?
Inquiry submitted 03/20/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 03/20/2018


Response #2:
No, a Stormwater Annual Report will not be required. Please bid per the current contract documents.
Response posted 03/26/2018




Inquiry #5: Traffic Chart G1 describes closures from May through June of any year.

Traffic Chart G2 describes closures from July through September of any year.

What's the deal with October through April of any year?

Inquiry submitted 03/27/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 03/27/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, March 30, 2018.
Please bid per the current contract documents.
Response posted 03/30/2018




Inquiry #6: Addendum 2 clarified some lane closure questions, but what are the lane closure requirements for November 1 - April 1? Can any work, including placing bird exclusion devices, be done during this time frame? Please advise.
Inquiry submitted 04/06/2018

Response #1:Your inquiry has been received and is being reviewed.
Response posted 04/06/2018


Response #2:Daily lane closure is allowed during those period for the required work, however, no night time lane closure and no K-rail installation is allowed.
Response posted 04/10/2018




Inquiry #7: How many trains per day pass over the bridge?
Inquiry submitted 04/09/2018

Response #1:Your inquiry has been received and is being reviewed.
Response posted 04/09/2018


Response #2:UPRR does not disclose the number or timing of trains passing over the bridge. Railroad traffic varies with market conditions.


Response posted 04/10/2018




Inquiry #8: Per the right of way agreement with the railroad, Exhibit A shows a cost estimate for flagging and inspection of $209,300. Is the state responsible for all railroad flagging and inspection costs by the UPRR? Please advise.
Inquiry submitted 04/10/2018

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 04/10/2018


Response #2:State is responsible for RR flagging and inspection cost by the UPRR.
Response posted 04/10/2018




Inquiry #9: What are the requirements for the protective covering over railroad? Please direct to specification / requirements.
Inquiry submitted 04/10/2018

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 04/10/2018


Response #2:Please refer to project Specifications under the following sections:
1- 48-8.01C(2) shop drawings 2nd to last paragraph #1 - Protective covers.
2- 60-2.02A(3) bridge removal work plan #7 - protective covers
3- 60-2.02C(1) & (2) railroad minimum construction clearance envelope.
The contractor is responsible for protecting the RR during the contractor?s operations.
4- 55-5.01C(4) shop drawings
5- 59-1.03A
Response posted 04/11/2018




Inquiry #10: Where in the plans or specifications are the requirements for the protective covering of the railroad area?
Inquiry submitted 04/10/2018

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 04/10/2018


Response #2:Please refer to project Specifications under the following sections:
1- 48-8.01C(2) shop drawings 2nd to last paragraph #1 - Protective covers.
2- 60-2.02A(3) bridge removal work plan #7 - protective covers
3- 60-2.02C(1) & (2) railroad minimum construction clearance envelope.
The contractor is responsible for protecting the RR during the contractor?s operations.
4- 55-5.01C(4) shop drawings
5- 59-1.03A
Response posted 04/11/2018




Inquiry #11: For clarification in regards to your answer to Inquiry #6, can we take any lane closures during the November 1 - April 1 time frame?
Inquiry submitted 04/10/2018

Response #1: Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 04/10/2018


Response #2:It is allowed to take lane closure one at a time (never close both lanes) during those periods.
Response posted 04/10/2018




Inquiry #12: On plan sheet 47 it calls for the contractor to survey the deck existing elevations before overlay removal. There are no control points on the plans referenced, where can these be found? Will control points be provided? Under what item will this work be paid?
Inquiry submitted 04/10/2018

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 04/10/2018


Response #2:No control points will be provided.
This item of work will be paid for under various items of work.
Your attention is also directed to note on page 47 "Contractor must provide grade control placement system".

Response posted 04/11/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.