Inquiry #1: Sheet number 125, E-20 shows the Fiber optic trench transitioning to the existing paved section per note 3. This transition takes place at approx station 127+85. It appears that this new Fiber Optic conduit run remains in the existing pavement section all the way to station 161+00, see sheet number 128, E-23. Can the department please confirm that our assumption is correct ?
Inquiry submitted 05/11/2018

Response #1:
(#1)-Your inquiry has been received and is being reviewed.
Response posted 05/11/2018


Response #2:
The assumption is correct. Your attention is also directed to section 15-1.03A, ?Existing Facilities? of the Standard Specifications.
Please bid per the contract documents.

Response posted 05/15/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.