Inquiry #1: For items 15 & 16 there is only one manufacturer that will warranty the material. Also the installation of the tape in areas prone to snowfall could lead to premature failure. These two factors will lead to inflated pricing for the item which is currently substantially more than other alternative striping methods.
Inquiry submitted 01/04/2018

Response #1:Your inquiry has been received and is being reviewed.
Response posted 01/04/2018


Response #2:
Please bid per the current contract documents.
Response posted 01/08/2018




Inquiry #2: The Departments attention is directed to the contract items presently listed in the Bid Schedule for the installation of Traffic Stripe Tape (WARRANTY). The specifications for the warranty of this tape are so narrowly tailored it restricts competition between competent vendors by favoring a “sole" source (3M Company). Sole sourcing of materials on Public Works projects is strictly forbidden and the Department and Supplier are treading on the lines of Anti-Trust.

Further, Public Contract Code ARTICLE 4, Preference for Materials SECTION 3400, states in part, “(a) The Legislature finds and declares that it is the intent of this section to encourage contractors and manufacturers to develop and implement new and ingenious materials, and services that function as well, in all essential respects, as materials, products and services that are required by a contract, BUT AT A LOWER COST TO THE TAXPAYERS." Taxpayers will be burdened by the increase in striping this project if Tape is employed as currently specified.

SECTION 3400 Further states “No agency of the state, charged with the letting of contracts for the construction or repair of public works, shall draft or cause to be drafted specifications for bids, (1) in a manner that limits the bidding, directly or indirectly, to any one specific concern”.

The Departments attention is further directed to the California Cartright Act and the Federal Sherman Act.

Please remove or revise the warranty requirements to allow open and fair competition between the tape vendors, or eliminate tape altogether and stripe the project entirely in thermoplastic.

Inquiry submitted 01/10/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 01/11/2018


Response #2:
Please bid per the current contract documents.
Response posted 01/17/2018




Inquiry #3: Section 84-3 contrast striping, how will this work be paid for? There are approx. 475,499LF of contrast striping (all of the (ModB) thermoplastic striping details) that currently have no pay item. Please advise.
Inquiry submitted 01/10/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 01/11/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Wednesday, January 17, 2018.
Please bid per the current contract documents.
Response posted 01/17/2018




Inquiry #4: Do the item quantities take into consideration the "coincident or adjacent contracts" listed on page 5 of the special provisions?
Inquiry submitted 01/16/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 01/16/2018


Response #2:
Your attention is directed to the “STRIPE AND MARKER EXCLUSION LOCATIONS” table on plan sheet PDQ-1.
Please bid per current contract documents.
Response posted 01/17/2018




Inquiry #5: Should the contractor consider this a flex start job that must begin before July 24, 2018?
Inquiry submitted 01/16/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 01/16/2018


Response #2:
Your attention is directed to Section 8, "PROSECUTION AND PROGRESS", of the Contract Special Provisions.
Please bid per current contract documents.
Response posted 01/17/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.