Inquiry #1: There is a construction detail for post placement on sheet 9 which is C-6 for w-beam post detail reduced embankment width. The summary of quantities sheet doesn't show any quantities for reduced embankment. Is Caltrans projecting there is some locations with the reduced embankment and if so how many locations and footage.
Inquiry submitted 11/22/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 11/22/2017


Response #2:
The detail for reduced embankment width was provided should the situation requiring it occur in the field. No areas with reduced embankment are expected at this time. Please bid per the current contract documents.
Response posted 11/30/2017




Inquiry #2: Re: Moving lane closer for striping.
It is highly irregular that this job does not have moving lane closer for striping and reflectors on this project. This would be a major project to stripe and ref with cones what normally would be extremely easy. In turn this would be pricey. Please reconsider. Also there are no spec's for striping. We assume sprayable is 40 mil but 1-5 should be thicker thermo. Thank You

Inquiry submitted 11/28/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 11/28/2017


Response #2:
Moving lane closures were not approved for this contract. Your attention is directed to Section 84-2.03C(2)(c), "Sprayable Thermoplastic Traffic Stripes and Pavement Markings", of the Standard and Revised Standard Specifications. Please bid per the current contract documents.
Response posted 11/30/2017




Inquiry #3: Item 4 Temporary Pavement Marking (Tape) has no corresponding removal item with it. If it is the intention of Caltrans that this temporary delineation is to be installed after the cold planing operation then there will be issues with the product adhering to the rough surfaces. Alternative temporary delineation, such as paint, could be used which would be more appropriate in this situation.
Inquiry submitted 12/11/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 12/11/2017


Response #2:
Your attention is directed to Section 39-3.04 and Section 12-6.03A of the Standard Specifications. Please bid per the current contract documents.
Response posted 12/11/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.