Bidder Inquiries

Sign In | Create Account

Viewing inquiries for 02-0E1804

Submit new inquiry for this project


Inquiry #1: Please advise what the wall thickness is for 36" Permanent Steel Casing called out for at the Abut 5 CIDH Pile locations.
Inquiry submitted 10/06/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/06/2017


Response #2:
Your attention is directed to Section 49-3.02C(6), paragraph 2, item 1 of the Standard Specifications for Contractor designed casing thickness criteria.
Please bid per the current contract documents.
Response posted 10/10/2017




Inquiry #2: Will there be an organized site visit?
Inquiry submitted 10/10/2017

Response #1:Your inquiry has been received and is being reviewed.
Response posted 10/10/2017


Response #2:
There will not be an organized site visit.
Please bid per the current contract documents.
Response posted 10/11/2017




Inquiry #3: Can you please provide AutoCAD files containing Existing and Design contours?
Inquiry submitted 10/17/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/17/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 1, issued on Thursday, October 26, 2017.
Please bid per the current contract documents.
Response posted 10/27/2017




Inquiry #4: The #5 end diaphragm between girder stirrups identified in the Part End Diaphragm Elevation on Sheet 22 of 37 are indicated as stainless steel (single asterisk). In Section B-B, they are indicated as epoxy coated. Please clarify.
Inquiry submitted 10/23/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/23/2017


Response #2:
Your attention is directed to plan sheet No. 96 of 111. The vertical stirrup diaphragm bars are stainless steel and the horizontal bars are epoxy coated, as shown. Please bid per the current contract documents.
Response posted 10/24/2017




Inquiry #5: The #5 end diaphragm between girder stirrups identified in the Part End Diaphragm Elevation on Sheet 22 of 37 are indicated as stainless steel (single asterisk). In Section B-B, they are indicated as epoxy coated. Please clarify.
Inquiry submitted 10/23/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/23/2017


Response #2:
Your attention is directed to plan sheet No. 96 of 111. The vertical stirrup diaphragm bars are stainless steel and the horizontal bars are epoxy coated, as shown. Please bid per the current contract documents.
Response posted 10/24/2017




Inquiry #6: Will permanent steel deck forms and/or permanent precast deck forms be allowed on this project?
Inquiry submitted 10/23/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/23/2017


Response #2:
Your attention is directed to Section 51-1.03C(2)(C)(i), of the Standard Specifications. Permanent steel deck forms are only allowed where shown or if specified as an option in the Special Provisions. Permanent precast deck forms are not an option in the Special Provisions, therefore permanent precast deck forms are not allowed. Please bid per the current contract documents.
Response posted 10/24/2017




Inquiry #7: Construction detail C-7 sheet 12 and structure drawing 78 show limits for excavation and backfill at abutment 5.

On drawing C-7 it is unclear what pay item the "Indicates excavation" legend references. Please Clarify.

Numerous dimensional conflicts exist between the drawings. Please Clarify.

Please verify structure excavation, structure backfill, and structure backfill impervious quantities.

Thanks

Inquiry submitted 10/24/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/24/2017


Response #2:
Your attention is directed to sheets No. 12 and 78 of 111 of the project plans. The detail on plan sheet No. 78 is shows the pay limits of both Structure Excavation and Structure Backfill. Structure Excavation will be paid under Bid item 34, while both Structure Backfill and Structure Backfill (Impervious) are paid under Bid item 35. Plan sheet No.12, Construction Detail sheet C-7, shows the maximum allowable limits for the structure excavation, as per our regulatory agency permits. Please bid per the current contract documents.
Response posted 10/25/2017




Inquiry #8: Special Provision 14-6.10 Requires bird exclusion devises (BED) to be installed between September 2 and January 31.

If the contract is not awarded prior to January 31 2018, will Caltrans install the BED so work can be performed in the 2018 construction season or will this become a 2019 project because there is no 2018 BED in place.


Inquiry submitted 10/24/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/25/2017


Response #2:
Please bid per the current contract documents.
Response posted 10/27/2017


Response #3:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/03/2017




Inquiry #9: Electrical Quantities Drawing 41 of 111 (aka E-7) references 200 LF of Boring, but no boring is specified within Temp Signal System Drawings 35 thru 37 of 111 (aka E-1 thru E-3). Please identify where the 200 LF of Boring shall be performed.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/30/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/03/2017




Inquiry #10: For the existing HAR Flasher to be maintained, please confirm it currently has photovoltaic panels. (No such power feed info appears to be provided in the documents or the Info Handout.)
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/30/2017


Response #2:
The existing HAR Flasher has no photovoltaic panels.
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #11: The Notice to Bidders indicates bids must be on a cost+time basis. Please indicate the daily value of the time component.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/30/2017


Response #2:
Your attention is directed to page 9 of the Bid Book for the daily value of time.
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #12: Special Provisions Section 12-4.02C(7)(b) indicates the max length of a single stationary one-way-reversing traffic-control lane closure is 0.75 miles between flaggers or signals. As currently shown, the Hwy 89 temp signals (and most of their signal loops) are located within the limits of the pavement section to be reconstructed. At Contractor's option, may the location of both Hwy 89 temp signals (and their signal loops) be extended beyond the limits of the pavement reconstruction - provided these temp signals remain separated by no more than 0.75 miles?
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/30/2017


Response #2:
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #13: Note 3 on Drawing 17 of 111 references Construction Stages 1 and 2. Please provide Stage Construction Drawings for Stages 1 and 2.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/03/2017




Inquiry #14: Please confirm that the temporary Type CL-6 fence shown on Dwg 18 of 111 is indeed temporary and not permanent. (Please confirm that the Chain Link Fence Revised Standard Plan Dwg 58 of 111 currently included with the Bid Set has been included in case permanent fence scope is added at later date.)
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
Your attention is directed to Section 80-1.02 of the Standard Specifications, temporary fence.
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #15: Please provide the thickness of the asphalt pavement on the existing bridge deck. (This is not currently addressed in the as-builts nor in the Pavement Coring Record included with Info Handout.)
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/06/2017




Inquiry #16: For the existing 3" electrical conduits shown at both EODs, please advise if either of these are live and must be temporarily maintained or if they shall be scheduled for demolition with the bridge. If either conduit is live and shall be maintained, please provide (1) further detail of the nature of these electrical services and (2) further detail for these services' permanent installation upon the new bridge.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/06/2017




Inquiry #17: Presuming that Contract Award occurs early enough to afford Contractor installation of the BED prior to the January 31st migratory bird nesting season (reference other Bidder's Inquiry #8) please confirm that this BED work will NOT be considered a job site activity which would otherwise (1) start and exhaust most of the Contract Time prior to being able to gain access to the Spillway on May 1st and (2) require the preceding development, submission, and Department acceptance of Contractor's SWPPP.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, November 3, 2017.
Please bid per the current contract documents.
Response posted 11/03/2017




Inquiry #18: Special Provisions Section 12-3.36C indicates to place portable transverse rumble strips as shown. Please provide these locations.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
Your attention is directed to Standard Plan T-13, for layout of the portable transverse rumble strips.
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #19: Given Drawing Sheet 12 of 111 indicates the max allowable limits for excavation per regulatory agency permits (reference other Bidder Inquiry #7), please advise if this similarly applies to the near vertical excavation limits delineated on previous Drawing Sheet 11 of 111 or if it will be acceptable to lay back those excavation slopes beyond those delineated limits.
Inquiry submitted 10/30/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 10/31/2017


Response #2:
All excavation work for Abutment 1 and 5 should be within the limits as shown on sheet 11 and 12. The final pay limits are as shown on sheet 78 of 111.
Please bid per the current contract documents.
Response posted 11/02/2017




Inquiry #20: Please confirm that there are no work hour restrictions/limitations for this project. (Neither the Specs nor the provided permit(s) indicate any such restrictions.)
Inquiry submitted 11/02/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 11/02/2017


Response #2:
Please bid per the current contract documents.
Response posted 11/06/2017




Inquiry #21: Building the bridge will require setting up a crane on the existing concrete spillway floor slab. Can you provide a load rating or design criteria in order to design and install temporary runways to protect the floor slabs from breaking and/or the design to rebuild the floor slabs when they break due to insufficient load protection?
Inquiry submitted 11/03/2017

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 11/06/2017


Response #2:
Please refer to the first paragraph of section 15-1.03A of the Special Provisions. The Contractor must provide all means necessary to protect the spillway walls and floor from damage. You may request to view the as-built drawings of the spillway floor upon contract award.
Please bid per the current contract documents.
Response posted 11/07/2017




Inquiry #22: For scheduling purposes for the estimate, when is the estimated notice to proceed date? When does the 125 day window start?
Inquiry submitted 11/06/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/07/2017


Response #2:
Your attention is directed to Section 3, “CONTRACT AWARD AND EXECUTION” and Section-8-1.04, “START OF JOB SITE ACTIVITIES”, of the standard specifications.
Please bid per contract documents.
Response posted 11/09/2017




Inquiry #23: In reference to Addendum 2, please confirm that the entry to the jobsite to measure controlling field dimensions, locate utilities, and to install bird exclusion devices on the bridge without excavating or grading does not constitute starting job site activities (and consequently does not constitute the start of Contract Time.)
Inquiry submitted 11/08/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/09/2017


Response #2:
Your attention is directed to Section 8-1.02 of Standard Specifications and Section 8-1.04C of the Special Provisions to determine the relationship between the contractor’s schedule and the start of working days.
Please bid per contract documents.
Response posted 11/13/2017




Inquiry #24: Addendum #2 affords access to install bird exclusion devices on the existing bridge without excavating or grading prior to February 28th. Please advise if the dam spillway may also be accessed prior to February 28th in order to install these devices. (Work within the dam spillway is currently authorized only between May 1st and October 31st.)
Inquiry submitted 11/08/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/09/2017


Response #2:
Your attention is directed to Addenda 2, Section 8-1.04C of the Special Provisions.
Please bid per the current contract documents.
Response posted 11/09/2017




Inquiry #25: The Special Provisions indicate that (among other conditions) closure of the existing bridge to public traffic will constitute the start of the allowable 20 day period to construct the "C1" line detour and that the end of this period is achieved when the detour is open for traffic.

However, Special Provisions Chart K1 is silent on this 20 day allowable closure of Hwy 89. Please clarify.

Inquiry submitted 11/08/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/09/2017


Response #2:
Because two lanes will be available to public traffic by utilizing the detour on Hwy-147, the requirement in chart K-1, to provide at least 1 through traffic lane not less than 12 feet in width for use by both directions of travel, will be met.
Please bid per the current contract documents.
Response posted 11/09/2017




Inquiry #26: Inquiry #15 requesting clarification of the asphalt thickness on the bridge deck does not appear to have been addressed in Addendum #2. Please advise.
Inquiry submitted 11/08/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/09/2017


Response #2:
Please refer to bridge As-builts for the AC thickness on the bridge deck.
Please bit per contract documents.
Response posted 11/09/2017




Inquiry #27: In reference to the Pier Cap Pour Sequence indicated on Dwg 78 of 111, please confirm the drop cap (pour 1) has been designed to adequately support the girders during their erection - prior to the pier cap diaphragm pour - such that no temporary bracing of the drop cap is required due to the girder loading.
Inquiry submitted 11/12/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/13/2017


Response #2:The sequence of erection and removal of the pier cap falsework is not indicated in the contract documents. Contractor to bid per the current contract bid documents.
Response posted 11/13/2017




Inquiry #28: The project specific CDFW 1600 states:
2.3 Bridge-dwelling Wildlife Protection. Exclusionary devices shall be installed on the bridge prior to the initiation of nesting season (February 1).
The addendum, which modifies the installation window to Sept 2 - Feb 28, is now not in alignment with project permit.
Additionally, installation of these devices after February 1 requires a pre-construction survey to avoid impacts to nesting birds.
1. Will Caltrans be performing this pre-con inspection?
2. Will Caltrans be modifying the 1600 agreement so submission of notification of construction does not identify conflicts of work timing with permit requirements?
3. Or, will Caltrans be performing notifications?

Inquiry submitted 11/14/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/15/2017




Inquiry #29: Please refer to note on Page 42 of the special provisions. "Add to Section 49-3.02C(6): Install permanent steel casings by oscillators." -

We assume that this is to allow oscillator use, but casings can also be installed by the methods also outlined in 49-3.02C(6), as well as installed by rotation, and vibration.

Please confirm

Inquiry submitted 11/15/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 11/15/2017


Response #2:Your assumption is not correct. Bid per the current contract documents.
Response posted 11/15/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.