Inquiry #1: Plans call for construction area signs to be on sheet #7-9, but there are no signs shown. Please provide the sign plans for construction area signs.
Inquiry submitted 09/18/2017

Response #1:Your inquiry has been received and is being reviewed.
Response posted 09/18/2017


Response #2:An addendum is being prepared to address this inquiry.
Response posted 10/03/2017


Response #3:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Friday, October 6, 2017.
Please bid per the current contract documents.
Response posted 10/06/2017




Inquiry #2: Item 14 Roadway Excavation show quantity of 200 CY. The schedule of quantities on sheet Q-1 of plans shows quantity of 489.18 CY. Please advise as to which is correct.

Item 19 Compost show quantity of 550 CY at location 2. Quantity appears to be incorrect for area of coverage. Please advise as this will inflate bid amount substantially.

Inquiry submitted 09/29/2017

Response #1:Your inquiry has been received and is being reviewed.
Response posted 09/29/2017


Response #2:An addendum is being prepared to address this inquiry.
Response posted 10/03/2017


Response #3:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 3, issued on Friday, October 6, 2017.
Please bid per the current contract documents.
Response posted 10/06/2017




Inquiry #3: Where do we obtain the willow cuttings?
Inquiry submitted 10/06/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 10/06/2017


Response #2:
Your attention is directed to Section 20-3.01B(2)(b)(iii), Willow Cuttings, of the 2015 Standard Specifications.
Please bid per the current contract documents.
Response posted 10/09/2017




Inquiry #4: Can we dispose of the excavated materials on site?
Inquiry submitted 10/06/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 10/06/2017


Response #2:
Your attention is directed to section 7-1.02K(6)(j)(iii) of the project Special Provisions.
Please bid per the current contract documents.
Response posted 10/23/2017




Inquiry #5: All the locations have work that is within creek limits. Work within the creek is limited to June 15 and Oct 15 per section 13-12.03A. Section 20-3.01B(2)(v) requires us to plant the willow polls between September 15 and October 15. If we start the job June 15, after the 40 days expires, do we need to include liquidated damages until the willow cuttings work can take place?

Inquiry submitted 10/06/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 10/06/2017


Response #2:
Your attention is directed to Section 1-1.07, "working day", as well as Sections 8-1.05, "Time" and 8-1.06 "Suspensions" of the Standard Specifications.
Please bid per the current contract documents.
Response posted 10/10/2017




Inquiry #6: Section 20-10.03C(3)(a) requires us to water the alder until 10-15-18, if we started the work in June, the contract time would run out while we are still required to perform certain work. Should the watering item be eliminated from the contract and be given to maintenance crews?
Inquiry submitted 10/06/2017

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 10/06/2017


Response #2:
Your attention is directed to Section 1-1.07, "working day", as well as Sections 8-1.05, "Time" and 8-1.06 "Suspensions" of the Standard Specifications.
Please bid per the current contract documents.
Response posted 10/10/2017




Inquiry #7: At site 1 the access is limited and full of vegetation. Will we be able to pioneer access from the down stream side or access the creek from another location and walk equipment/materials in? Do we need to figure on using a crane to place equipment and materials?
Inquiry submitted 10/06/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 10/06/2017


Response #2:A TCE is shown on project plan sheet 2 of 26, L-1. Please bid per the current contract documents.
Response posted 10/09/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.