Chico Auxiliary Lanes Phase 2 Project


DESCRIPTION

Widen the roadway shoulders adjacent the Rock Creek Bridge on Highway 99.

PROJECT BENEFITS

This project increases motorists safety by widening shoulders and enhancing the approaches to the Rock Creek Bridge on Highway 99 north of Chico. The shoulders will be widened to eight feet and rumble strips will be added.

FUNDING BREAKDOWN

State - $3,400,000
Federal - $0
Total - $3,400,000

PROJECT SCHEDULE

Environmental Document Completed - January 2013
Right of Way Acquisition Completed - September 2014
Design Completed -October 2014
Advertise: January 2015
Begin Construction: May 2015
Expected Completion: January 2018

PARTNERSHIP

Caltrans

PROJECT CONTACT

Rodney Murphy, Project Manager
Phone: (530) 741-5127
Email: rodney.murphy@dot.ca.gov

Gilbert Mohtes-Chan, Public Information Officer
Phone: (530) 741-4571
Email: gilbert.mohtes-chan@dot.ca.gov

NO ADDITIONAL DOCUMENTS AVAILABLE

NO NEWS AVAILABLE

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.