Curve Realignment on SR 174 in Nevada County


DESCRIPTION

The project proposes to realign several curves, widen shoulders, add a left-turn lane at Greenhorn Access Rd, and improve the Clear Recovery Zone (CRZ) on State Route (SR) 174 from post mile PM 2.7 to PM 4.6 in Nevada County, California

PROJECT BENEFITS

The purpose of this project is to improve safety and operations for all users, including bicyclists, and pedestrians. This project proposes to help reduce the number and severity of collisions within this segment of SR 174.

FUNDING BREAKDOWN

Local - $0
State - $3,131,000
Federal - $25,325,000
Estimated Total Project Cost - $28,456,000

PROJECT SCHEDULE

Environmental Document Completed -- 9/2/2016
Right of Way Acquisition Completed --2/1/2019
Design Completed -- 2/1/2019
Advertise -- 4/1/2019
Begin Construction -- 9/1/2019
Expected Completion -- 10/1/2020

PARTNERSHIP

none

PROJECT CONTACT

Jonathan Pray, Project Manager
Phone: (530) 740-4920
Email: Jonathan.Pray@dot.ca.gov

Liza Whitmore, Public Information Officer
Phone: (530) 741-4566
Email: liza.whitmore@dot.ca.gov

Announcements:

Caltrans has been invited to present a project update to the Nevada County Board of Supervisors at 1:30 p.m. Tuesday, October 24 at their chambers in the Eric Rood Administrative Center at 950 Maidu Avenue, Nevada City. Information about how the project’s scope has been modified to address community concerns will be included in the presentation. A future evening public meeting is also planned.

Public Notification Documents:

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.