Curve Realignment on SR 174 in Nevada County


DESCRIPTION

The project proposes to realign several curves, widen shoulders, add a left-turn lane at Greenhorn Access Rd, and improve the Clear Recovery Zone (CRZ) on State Route (SR) 174 from post mile PM 2.7 to PM 4.6 in Nevada County, California

PROJECT BENEFITS

The purpose of this project is to improve safety and operations for all users, including bicyclists, and pedestrians. This project proposes to help reduce the number and severity of collisions within this segment of SR 174.

FUNDING BREAKDOWN

Local - $0
State - $3,131,000
Federal - $25,325,000
Estimated Total Project Cost - $28,456,000

PROJECT SCHEDULE

Environmental Document Completed -- 9/2/2016
Right of Way Acquisition Completed --2/1/2019
Design Completed -- 2/1/2019
Advertise -- 4/1/2019
Begin Construction -- 9/1/2019
Expected Completion -- 10/1/2020

PARTNERSHIP

none

PROJECT CONTACT

Cameron Knudson, Project Manager
Phone: (530) 741-4587
Email: Cameron.Knudson@dot.ca.gov

Liza Whitmore, Public Information Officer
Phone: (530) 741-4566
Email: liza.whitmore@dot.ca.gov

Announcements:

Caltrans will hold an Open House on May 24, 2017 from 5 – 6:30 p.m. at the Chicago Park Elementary School at 15725 Mt. Olive Drive in Grass Valley to share the latest information and project design. The public is welcome to drop in anytime.

Public Notification Documents:

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.