Highway 193 Newcastle Realignment Project


DESCRIPTION

This realignment project will improve the radius of the roadway curves, increase sight distance, add paved shoulder width, and provide clear recovery zones.

PROJECT BENEFITS

Improved motorist safety with increase sight distance, paved shoulders and eased corner radius.

FUNDING BREAKDOWN

Local -
State - $17 million
Federal -
Estimated Total Project Cost - $17 million

PROJECT SCHEDULE

Environmental Document Completed -- March 2013
Right of Way Acquisition Completed -- December 2014
Design Completed -- November 2014
Advertise -- March 2015
Begin Construction -- June 2015
Expected Completion -- October 2017

PARTNERSHIP

none

PROJECT CONTACT

John Holder, Project Manager
Phone: (530) 741-5448
Email: john.holder@dot.ca.gov

Liza Whitmore, Public Information Officer
Phone: (530) 741-4572
Email: liza.whitmore@dot.ca.gov

Environmental Documents:

NO NEWS AVAILABLE

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.