Meeks Bay Storm Water Quality Improvements and Pavement Rehabilitation


DESCRIPTION

Storm water quality improvements, pavement rehabilitation on Highway 89 from Meeks Creek to Wilson Avenue in Tahoma.

PROJECT BENEFITS

The project will improve the quality of roadway runoff by installing curbs and gutters and drainage systems to collect and treat stormwater. It will also improve the roadway surface.

FUNDING BREAKDOWN

Local -
State - 20%
Federal - 80 %
Estimated Total Project Cost - $8,095,000

PROJECT SCHEDULE

Environmental Document Completed -- October 2012
Right of Way Acquisition -- January 2014
Design -- January 2014
Advertise -- January 2014
Begin Construction -- Spring 2015
Expected Completion -- Fall 2015

PARTNERSHIP

none

PROJECT CONTACT

Rodney Murphy, Project Manager
Phone: (530) 741-5127
Email: rodney.murphy@dot.ca.gov

Steve Nelson, Tahoe Basin Outreach Coordinator
Phone: (530) 741-4566
Email: steve.nelson@dot.ca.gov

NO ADDITIONAL DOCUMENTS AVAILABLE

NO NEWS AVAILABLE

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.