Tower Bridge Maintenance Project


Tower Bridge at Night

DESCRIPTION

This is a HM315 project for mechanical and electrical rehabilitation on Tower Bridge, located in Yolo County on Route 275, PM 13.01. The work will upgrade the existing security/communications system, replace 48 incandescent lights with energy efficient LED lighting, replace the traveling cable system, conduct NDS testing and maintenance of the counter balance chains, and replace the 96 counterweight wire ropes, required to operate the bridge opening.

PROJECT BENEFITS

Replacing the highlighted mechanical and electrical facilities with updated equipment and materials will continue to ensure marine vessels can safely navigate the channel.

FUNDING BREAKDOWN

Local - N/A
State - $5.8 million
Federal – N/A
Estimated Total Project Cost - $5.8 million

PROJECT SCHEDULE

Environmental Certification Completed -- December 2017
Right of Way Certification Completed -- October 2017
Design Completed -- March 2018
Advertise -- April 2018
Begin Construction -- September 24, 2018
Expected Completion -- December 2018

PARTNERSHIP

none

PROJECT CONTACT

Sameh A. Hegazi, Project Manager
Phone: (530) 741-4319
Email: sameh.hegazi@dot.ca.gov

Dennis Keaton, Public Information Officer
Phone: (530) 741-4574
Email: dennis.keaton@dot.ca.gov

NO DOCUMENTS AVAILABLE

NO NEWS AVAILABLE

Tower Bridge Images:









News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate